No. Project Name Owner Facility Duration Description
1 Moho Nord TLP Total, Congo TLP May 2016 -
Dec 2016
Construction (Installation of E & I Equipment and Materials, etc.), Mechanical Completion, Trouble Shooting, Punch Clearance, Commissioning, and Handover
2 Moho Nord FPU Total, Congo FPU May 2016 -
Dec 2016
Construction (Installation of E & I Equipment and Materials, etc.), Mechanical Completion, Trouble Shooting, Punch Clearance, Commissioning, and Handover including Living Quarter
3 Aasta
Hansteen
SPAR
Statoil, Norway SPAR Jan 2015 -
Dec 2016
Construction (Installation of E & I Equipment and Materials, etc.), Mechanical Completion, Trouble Shooting, Punch Clearance, Cold Loop Test, and Handover
4 Aasta
Hansteen
Topside
Statoil, Norway Topside Jan 2015 -
Dec 2016
Construction (Installation of E & I Equipment and Materials, etc.), Mechanical Completion, Trouble Shooting, Punch Clearance, Commissioning, and Handover including Living Quarter
5 Clair Ridge BP, UK Platform Sep 2015 -
Feb 2016
Construction (Installation of E & I Equipment and Materials, etc.), Mechanical Completion, Trouble Shooting, Punch Clearance, Commissioning, and Handover including Living Quarter
6 Quad 204 BP, UK FPSO Apr 2013 -
Nov 2015
Construction (Installation of E & I Equipment and Materials, etc.), Mechanical Completion, Trouble Shooting, Punch Clearance, Commissioning, and Handover including Living Quarter
7 Goliat ENI, Norway FPSO Apr 2012 -
Feb 2015
Construction (Installation of E & I Equipment and Materials, etc.), Mechanical Completion, Trouble Shooting, Punch Clearance, Commissioning, and Handover including Living Quarter
8 Gorgon LNG Chevron, Australia LNG Plant Nov 2011 -
Sep 2015
Construction (Installation of E & I Equipment and Materials, etc.), Mechanical Completion, Trouble Shooting, Punch Clearance, Commissioning, and Handover including Modular Buildings